By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

MANILA, Philippines – San Miguel Corp. (SMC) subsidiary Masinloc Power Co. Ltd. (MPCL) secured regulatory approval to construct and own P1.7-billion transmission facilities to connect its 700-megawatt (MW) coal plant to the national grid.

In a decision dated June 30, the Energy Regulatory Commission (ERC) said the dedicated point-to-point limited transmission assets would be linked to the Castillejos Substation and Palauig Substation of the National Grid Corp. of the Philippines (NGCP).

READ: ERC lets non-NGCP firms build transmission projects

The ERC, however, rejected the company’s request to also operate and maintain the facilities, with these tasks assigned to the NGCP.