The redevelopment works held at Ernakulam Junction railway station on July 26.
| Photo Credit: THULASI KAKKAT
The deadline for completing the redevelopment of Ernakulam Junction (ERS) and Ernakulam Town (ERN) railway stations has been revised to March 2028 and December 2028, respectively, following the re-tendering of the works.The Railway terminated the contracts of the firms concerned after they failed to adhere to the project timelines. The pending works at ERS were re-tendered earlier this year, while a similar process is under way for ERN station. When the works began in August 2022, the initial redevelopment costs of ERS and ERN were ₹300 crore and ₹150 crore, respectively, with August 2025 set as the deadline.
Redevelopment works progressing at Ernakulam Town railway station on July 25.
| Photo Credit: