A data center can be built in 18 to 24 months, but connecting it to the grid is another matter, writes Laura Hoffmann-Ostenhof, Europe industry lead at modeling software supplier Gridcog. Across Europe’s established hubs – the FLAP-D cluster of Frankfurt, London, Amsterdam, Paris and Dublin – the wait for a grid connection now runs from seven to 10 years, as data centers compete for capacity.