A feature takes three days to code and three weeks to deliver. The difference is not always engineering capacity.
A developer starts implementation and discovers that an eligibility rule is undefined. Product needs an answer from operations. A missing UX state appears next. Then engineering finds that the requested behavior conflicts with the current data model, which forces a scope decision.
The code may still take three days. The delivery system takes three weeks.
This is where product engineering alignment becomes an engineering leadership problem. The visible work happens in code, but much of the elapsed time happens between decisions: waiting for clarification, resolving constraints, revisiting scope, and discovering assumptions that should have surfaced earlier.
The common response is to improve requirements, add meetings, or demand better estimates. Those actions may help, but they do not address the core issue. Product-engineering alignment is primarily a decision-flow problem.