The Supreme Court has temporarily allowed President Donald Trump to continue working on a massive new ballroom at the White House, freezing a court ruling that would have required construction to stop at midnight Friday.
Friday afternoon’s order doesn’t address the legality of the project, which two other courts have said Trump is pursuing unlawfully because Congress hasn’t approved it. Instead, it’s meant to give the justices additional time to consider Trump’s request that the adverse rulings be paused indefinitely.
Construction has been progressing rapidly, with a 250-person crew working 20-hour days, 7 days per week, according to a filing submitted by the Trump administration to the Supreme Court. The government put the ballroom complex at “65% complete in its entirety.”