Australian thermal energy storage company 1414 Degrees has signed a non-binding heads of agreement with an unnamed data center firm to develop an up to 1GW AI project within the Aurora Energy Precinct, near Port Augusta in South Australia.

– 1414 Degrees

According to 1414, the data center will be a phased development, commencing with a 17MW campus supplied via the company’s existing 33kV network connection, supplemented by onsite solar and a Battery Energy Storage System (BESS).

Following this, the companies intend to expand to a 200MW anchor campus after expanding a 275kV transmission connection on the eastern side of the site, which they claim will offer a longer-term pathway toward gigawatt-scale deployment. The entire Aurora Precinct landholding spans 1,580 hectares.

The agreement will grant the unnamed operator exclusivity over an initial 40-hectare development parcel while 1414 negotiates definitive commercial agreements.