Pacific Gas and Electric now counts 12.7 GW in its data center pipeline, of which 490 MW of projects have executed interconnection agreements and another 3.9 GW are in final engineering, company officials said Thursday during a second-quarter earnings call.

The company’s data center pipeline has fluctuated over the past year, from 7.3 GW at the end of 2025 to 5.4 GW in the first quarter of 2026 as projects dropped out. The company’s most recent investor presentation Thursday retroactively revised down its queue from last quarter to 5.1 GW, citing changes to its methodology.

Executives attributed the changes to stricter vetting of potential projects and expressed confidence that their efforts to attract the right kind of customer are paying off.

PG&E Corporation CEO Patti Poppe said she expects to serve 1.8 GW of new data center load by 2030.