ISLAMABAD: In a case involving the multi-billion-rupee public project of Parliament Lodges extension that has remained unfinished for nearly 15 years, the Capital Development Authority (CDA) on Saturday mounted an attack on the arbitration award of over Rs643 million in favour of the contractor, alleging that the award was the product of “legal misconduct”, jurisdictional overreach and a complete disregard of contractual obligations.
The arguments were concluded before Additional District Judge (West) Amir Zia, who is hearing the CDA’s appeal against an earlier judgement.
The matter has now been adjourned until Sept 19.
Appearing for the CDA, Advocate Kashif Ali Malik argued that the case illustrated how “the victim has been turned into the accused”, with a public authority allegedly being directed to compensate a contractor whose project, according to the CDA, still stands incomplete years after its contractual completion date.