—Project cost Eneva is investing roughly R$6 billion (about US$1.2 billion) in the thermal plant and a dedicated gas pier, creating over 2,000 jobs during construction.

—Capacity and contract The Jandaia plant will generate 1,147 MW under a 15-year federal contract, expanding the region’s reliable power supply for investors and residents.

—LNG infrastructure The project includes an import terminal, an FSRU, and a R$430 million (about US$85 million) pier, securing a new natural gas supply route for Ceará.