Construction of the new MyCiTi bus station in Claremont is making progress, with the installation of 583 concrete piles now complete.
The City said the the piling forms the foundation on which the station building and future overhead development will be supported.
The project forms part of the MyCiTi bus service expansion that will connect Mitchells Plain and Khayelitsha with Claremont and Wynberg.
The old bus terminus along Claremont Boulevard, between Hawthorne Road and Newry Street, has been demolished and removed, and the construction of a new MyCiTi bus station is now under way in the heart of Claremont within walking distance from the Claremont railway station and the minibus-taxi facility in Ralph Street.