The airport's project management board said on June 10 it had energized the power system together with the Dong Nai Power Company, feeding electricity from a dedicated 110 kV substation into the receiving station run by Airports Corporation of Vietnam (ACV), the state-owned developer building the airport about 40 km east of Ho Chi Minh City.
Stable, continuous power is a prerequisite for what comes next: a series of trial runs that will test the terminal, baggage systems and ground operations before passengers arrive. ACV plans three rounds of trial operations in September, October and November, with official commercial service targeted for December 2026.
Long Thanh airport's power supply is officially switched on, June 2026. Photo by VnExpress/Thai Ha
The milestone caps a frantic stretch of construction. On June 1, ACV launched a 180-day sprint to finish the airport on time, a push that follows years in which the project wrestled with labor shortages, contractor payment delays and volatile material prices. Roughly 76% of the total project by value is now complete, and the most critical pieces are further along. The aircraft apron near the terminal is more than 88% finished, the fuel system more than 92%, and the connecting roads close to 90%. The passenger terminal, the centerpiece, has its main structure up and is about two-thirds of the way through interior work and equipment installation.






