Dive Brief:
Utilities are overstating how much time competitive solicitations can add to the transmission development process, the Midcontinent Independent System Operator told federal regulators on Wednesday in response to a complaint filed by incumbent companies seeking exclusive rights to build certain power lines.
“MISO disagrees with the exaggerated length of the delay alleged in the Complaint as MISO’s actual experience differs from the alleged 16-20-month timeframe,” the grid operator said in a filing with the Federal Energy Regulatory Commission.
Although MISO challenged assertions in the complaint, it stopped short of taking a position on whether FERC should grant or deny the utilities’ requested relief. Looking ahead, the dispute at FERC could affect who gets to build regional transmission projects in MISO and the Southwest Power Pool and could spill over into other regions.